Diesel gensets · silent canopy sets · temporary site power
A generator is sized on starting load, not running load, and then oversized twice — once for operating headroom and once because a diesel set loses output in UAE summer heat. Skip either step and the set trips when the largest motor starts, usually on the first hot afternoon. This page sets out the classes and the sizing method; the owner of the set quotes the rate.
| Class | Prime rating band | What it typically carries | Supply | Notes |
|---|---|---|---|---|
| Portable / small | 10–30 kVA | Site office, lighting, hand tools, a small mixer | Single or three phase | Often skid or trailer mounted, base fuel tank |
| Small site | 45–80 kVA | Fit-out or villa site: compressor, mixer, tools, lighting | Three phase, 400 V | Canopied sets standard |
| Mid site | 100–200 kVA | Mid construction site: hoists, pumps, welding, offices | Three phase, 400 V | External bunded tank becomes normal at this size |
| Large | 250–500 kVA | Tower or major site: tower crane, multiple hoists, distribution | Three phase, 400 V | Delivered on a low-bed; standing area and access for a fuel bowser |
| High capacity | 650 kVA and above | Infrastructure, plant, large temporary installations | Three phase, 400 V | Often two sets synchronised rather than one very large one |
UAE rental fleets step through standard sizes — 10, 20, 30, 45, 60, 80, 100, 125, 150, 200, 250, 300, 400, 500, 650 and 800 kVA. Your calculated requirement will land between two of them; the set you hire is the next one up.
The same physical set carries more than one rating. Prime is what it delivers continuously under a varying load, and it is the only rating to size site power on. Standby is an emergency rating for a set that runs occasionally, and it is a higher number for the same machine — a set advertised at 500 kVA standby may be roughly 455 kVA prime. Continuous is a lower rating again for constant unvarying load. If a quotation does not say which rating the kVA figure is, the figure does not mean anything yet.
Steps 4 and 5 together are a single factor of 1.5625 applied to the kVA figure.
| Site | Running load | Largest motor surge | kVA at 0.8 pf | × 1.5625 | Set to hire |
|---|---|---|---|---|---|
| Villa / small fit-out | 12 kW | +10 kW (5 kW mixer) | 27.5 kVA | 43 kVA | 45 kVA prime |
| Mid construction site | 40 kW | +22 kW (11 kW compressor) | 77.5 kVA | 122 kVA | 125 kVA prime |
| Tower / large site | 120 kW | +90 kW (45 kW crane) | 262.5 kVA | 411 kVA | 500 kVA prime |
Illustrative load lists, not a specification for your site. Run your own figures through the generator sizing calculator, then have the result checked by a qualified electrical engineer or the supplier's engineer before you commit.
Load factor is the average load the set actually carries divided by its rated output. Target a steady 70–80% of prime rating. A set running long hours at very light load — below roughly 30% — wet-stacks: unburnt fuel accumulates in the exhaust, the engine glazes, and the set runs progressively worse and dirtier. That is why the answer to an uncertain load is not simply the biggest set available. If the load profile is genuinely lumpy — heavy for a few hours, nearly idle the rest — two smaller sets, or a set plus a load bank arrangement, is the engineering answer.
Permit routes, certificate validity periods and working-hour rules differ by emirate, by authority and by free zone, and they change. Treat everything above as the questions to ask, not as a current legal position — confirm the requirement with the authority, the site and the equipment owner before the machine is booked.
Know the class you need?
Post the specification — class, size, dates, emirate — and the owners of the machines can contact you directly with their own rate and availability. Listing and posting are free, there is no commission, and MachineryRentalMarket is not a party to the rental contract.