Generator classes and sizing

Diesel gensets · silent canopy sets · temporary site power

A generator is sized on starting load, not running load, and then oversized twice — once for operating headroom and once because a diesel set loses output in UAE summer heat. Skip either step and the set trips when the largest motor starts, usually on the first hot afternoon. This page sets out the classes and the sizing method; the owner of the set quotes the rate.

The classes

ClassPrime rating bandWhat it typically carriesSupplyNotes
Portable / small10–30 kVASite office, lighting, hand tools, a small mixerSingle or three phaseOften skid or trailer mounted, base fuel tank
Small site45–80 kVAFit-out or villa site: compressor, mixer, tools, lightingThree phase, 400 VCanopied sets standard
Mid site100–200 kVAMid construction site: hoists, pumps, welding, officesThree phase, 400 VExternal bunded tank becomes normal at this size
Large250–500 kVATower or major site: tower crane, multiple hoists, distributionThree phase, 400 VDelivered on a low-bed; standing area and access for a fuel bowser
High capacity650 kVA and aboveInfrastructure, plant, large temporary installationsThree phase, 400 VOften two sets synchronised rather than one very large one

UAE rental fleets step through standard sizes — 10, 20, 30, 45, 60, 80, 100, 125, 150, 200, 250, 300, 400, 500, 650 and 800 kVA. Your calculated requirement will land between two of them; the set you hire is the next one up.

Prime, standby and continuous — the rating matters more than the number

The same physical set carries more than one rating. Prime is what it delivers continuously under a varying load, and it is the only rating to size site power on. Standby is an emergency rating for a set that runs occasionally, and it is a higher number for the same machine — a set advertised at 500 kVA standby may be roughly 455 kVA prime. Continuous is a lower rating again for constant unvarying load. If a quotation does not say which rating the kVA figure is, the figure does not mean anything yet.

How to size it — the method

  1. Sum the running loads in kW that will genuinely be on at the same time. Not everything on the site inventory runs together.
  2. Add the starting surge of the largest motor. A motor drawing X kW running pulls roughly three times that at start, so add about 2 × X kW on top of the running total. Only the largest motor — two large motors starting simultaneously is a sequencing problem to solve on site, not a reason to hire a much bigger set.
  3. Convert to kVA at a 0.8 power factor: kVA = peak kW ÷ 0.8.
  4. Add 25% operating headroom — × 1.25.
  5. Add 25% for UAE heat. Diesel output derates by roughly 1% per °C above 25 °C, so at 45 °C ambient the set is delivering around 20% less than its rated output. × 1.25.
  6. Round up to the next standard size from the list above, on the prime rating.

Steps 4 and 5 together are a single factor of 1.5625 applied to the kVA figure.

The method on three typical load pictures

SiteRunning loadLargest motor surgekVA at 0.8 pf× 1.5625Set to hire
Villa / small fit-out12 kW+10 kW (5 kW mixer)27.5 kVA43 kVA45 kVA prime
Mid construction site40 kW+22 kW (11 kW compressor)77.5 kVA122 kVA125 kVA prime
Tower / large site120 kW+90 kW (45 kW crane)262.5 kVA411 kVA500 kVA prime

Illustrative load lists, not a specification for your site. Run your own figures through the generator sizing calculator, then have the result checked by a qualified electrical engineer or the supplier's engineer before you commit.

Load factor — and why oversizing is not free

Load factor is the average load the set actually carries divided by its rated output. Target a steady 70–80% of prime rating. A set running long hours at very light load — below roughly 30% — wet-stacks: unburnt fuel accumulates in the exhaust, the engine glazes, and the set runs progressively worse and dirtier. That is why the answer to an uncertain load is not simply the biggest set available. If the load profile is genuinely lumpy — heavy for a few hours, nearly idle the rest — two smaller sets, or a set plus a load bank arrangement, is the engineering answer.

What sits around the set

UAE practice

Permit routes, certificate validity periods and working-hour rules differ by emirate, by authority and by free zone, and they change. Treat everything above as the questions to ask, not as a current legal position — confirm the requirement with the authority, the site and the equipment owner before the machine is booked.

What to state in the enquiry

Know the class you need?

Post the specification — class, size, dates, emirate — and the owners of the machines can contact you directly with their own rate and availability. Listing and posting are free, there is no commission, and MachineryRentalMarket is not a party to the rental contract.

Post a request List your equipment

Next

Other class references

Aerial work platforms · Excavators · Forklifts · Telehandlers · Mobile cranes